To view previous data,select   Date:                   
Drilling Progress Report as on 7-February-2012
Following table shows Drilling actuals(Mtrs) day wise(For KGM,RGM,BPA Regions)
Area|
Date---> 1 2 3 4 5 6 7
KGM 45 99 187 309 - 254 -
RGM 122 70 56.5 - 44 70.5 -
BPA 129 136.5 138 - - - -
Total 296 305.5 381.5 309 44 324.5
Drilling Progress Report as on 7-February-2012
Area MONTHLY(February ) YEARLY (2012)
Month target Monthly Actual(Prog) Yearly Target(till this month) Yearly Actual(Prog)
KGM 720 894 29620 21291.5
RGM 990 363 40690 32480.7
BPA 990 403.5 40690 20347.5
TOTAL 2700 1660.5 111000 74119.7